Q1. By providing QBAT relay, track length can be increased up to QBAT रिले उपलब्ध कराकर ट्रैक की लंबाई को बढ़ाया जा सकता है।
- A) 350 m
- B) 450m
- C) 750m
- D) 1000m
Correct Answer: 750m
Explanation: Explanation : QTA2 (With ACI= 50 V) and Shelf Type relays (With ACI= 50 V) are used for Track lengths up to 450 Mts. beyond which up to 750 Mts. QBAT (with 80 V ACI ) is used.
Q2. Sanction of excess over original sanctioned cost (abstract cost) due to reasons other than price escalation can be done by zonal railways upto मूल्य वृद्धि के अलावा अन्य कारणों से मूल स्वीकृत लागत (सार लागत) से अधिक की स्वीकृति क्षेत्रीय रेलवे द्वारा की जा सकती है।
- A) 10%
- B) 20%
- C) 50%
- D) 100%
Correct Answer: 20%
Explanation: Explanation : 70% ASTE 2024 The powers to sanction excess over abstract / original estimate on account of Material Modifications is limited to
Q3. Ethernet uses a physical address that is imprinted on the network interface card (NIC). How many bits are used for the above physical address. ईथरनेट एक भौतिक पते का उपयोग करता है जो नेटवर्क इंटरफेस कार्ड (एनआईसी) पर अंकित होता है। उपरोक्त भौतिक पते के लिए कितने बिट्स का उपयोग किया जाता है?
- A) 32-bit
- B) 64-bit
- C) 48-bit
- D) 128-bit
Correct Answer: 48-bit
Explanation: Explanation : For example, Ethernet uses a 6-byte (
Q4. Two Packet Single Stage system of tendering shall be followed for Works Tenders valuing above which value :- दो पैकेट वाली एकल चरण निविदा प्रणाली उन निर्माण निविदाओं के लिए अपनाई जाएगी जिनका मूल्य इससे अधिक है:-
- A) Rs 1 Crore
- B) Rs5 Crores
- C) Rs 10 Crores
- D) Rs 25 Crores
Correct Answer: Rs 10 Crores
Explanation: Explanation : 70% ASTE 2024 For all works contract tenders requiring techno-economic evaluation, 'Two Packet System' of tendering shall be the norm as far as possible. For inviting Works Tenders valuing more than
Q5. Program Evaluation Review Technique (PERT), a project management planning tool is a प्रोग्राम इवैल्यूएशन रिव्यू टेक्निक (PERT), एक प्रोजेक्ट मैनेजमेंट प्लानिंग टूल है।
- A) Time oriented technique
- B) Event oriented technique
- C) Activity oriented technique
- D) None of the options is correct
Correct Answer: Time oriented technique
Explanation: Explanation : The Program Evaluation Review Technique, or PERT, is a
Q6. In a work tender, if an offer is received without EMD within stipulated time period, how it should be dealt . किसी कार्य निविदा में, यदि निर्धारित समय अवधि के भीतर ईएमडी के बिना कोई प्रस्ताव प्राप्त होता है, तो उससे कैसे निपटा जाना चाहिए?
- A) EMD can be asked for submission at a later date
- B) EMD can be deducted from the bills
- C) Offer to be summarily rejected
- D) Tender committee can decide to accept or reject.
Correct Answer: Offer to be summarily rejected
Explanation: Explanation : The offers received from tenderers without EMD and/or tender cost shall be summarily rejected except where exemption is provided in the tender.
Q7. As per RDSO specification IRS:S 93/96, VRLA batteries / cells shall be charged at a constant voltage of आरडीएसओ विनिर्देश आईआरएस:एस 93/96 के अनुसार, वीआरएलए बैटरी/सेल को एक स्थिर वोल्टेज पर चार्ज किया जाना चाहिए।
- A) 2.00V
- B) 2.15V
- C) 2.20V
- D) 2.25V
Correct Answer: 2.25V
Explanation: Explanation :
Q8. The maximum stroke of IRS CLAMP TYPE Point machine is आईआरएस क्लैम्प टाइप पॉइंट मशीन का अधिकतम स्ट्रोक है
- A) 143mm
- B) 220mm
- C) 160mm
- D) 115mm
Correct Answer: 220mm
Explanation: Explanation : 143mm for IRS points 220m for IRS CLAMP Type.
Q9. Force Majeure Clause provided in Stores and Works contracts, in certain situations and circumstances beyond the control of both the parties, described as 'Acts of God', allows parties to स्टोर और निर्माण अनुबंधों में दिए गए अप्रत्याशित घटना खंड के तहत, दोनों पक्षों के नियंत्रण से परे कुछ स्थितियों और परिस्थितियों में, जिन्हें 'दैवीय आपदा' कहा जाता है, पक्षों को निम्नलिखित अधिकार प्राप्त होते हैं:
- A) Defer performance of their contractual obligations
- B) End the contract without financial repercussions on either side
- C) Both the options given are correct
- D) Neither of the options given are correct
Correct Answer: Both the options given are correct
Explanation: Explanation : 70% ASTE 2024
Q10. S&T works are sanctioned under which plan-head in the 'Pink book' ? 'पिंक बुक' में विज्ञान और प्रौद्योगिकी कार्यों को किस योजना के अंतर्गत स्वीकृत किया जाता है?
- A) 1100
- B) 3100
- C) 3300
- D) 6400
Correct Answer: 3300
Explanation: Explanation : PH 11 - New Lines PH 31 - Track Renewals