Q1. Beyond the farthest point the minimum number of spare conductors of the total conductors used shall be _________. ASTE 70% 2025. सबसे दूर के बिंदु से परे, उपयोग किए गए कुल कंडक्टरों में से अतिरिक्त कंडक्टरों की न्यूनतम संख्या _________ होगी। ASTE 70% 2025.
- A) 20%
- B) 5%
- C) 10%
- D) 30%
Correct Answer: 10%
Explanation: Explanation : RDSO guidelines Indian Railways Telecom Manual (IRTM) As per and related , while laying cables for signaling and telecom purposes, are to be provided for future use, maintenance flexibility, and fault isolation. "Beyond the farthest point, a minimum of 10% of the total number of conductors used shall be kept as spare, subject to a minimum of 2 conductors."
Q2. Network Management Systems of a data network use ______ protocol for management. ASTE 70% 2025 डेटा नेटवर्क के नेटवर्क प्रबंधन सिस्टम प्रबंधन के लिए ______ प्रोटोकॉल का उपयोग करते हैं। ASTE 70% 2025
- A) DNS
- B) SNMP
- C) OSPF
- D) none of the options
Correct Answer: SNMP
Explanation: Explanation : to monitor the health of the network. It is an essential tool for managing the complete data networks using based on open standards. The Network Management System can do various tasks like configuration, diagnostic, provisioning, security and originating various MIS reports to be utilized by the Network Manager. NMS also has the facility of performance monitoring through resource utilization graphs. As far as possible traffic logs from various network devices may be recorded at a central server for analysis SNMP protocol purposes. Network Management System (NMS) is an essential part of any data network
Q3. Works carried out for other departments, local bodies, private persons by the Railways are _____________. रेलवे द्वारा अन्य विभागों, स्थानीय निकायों, निजी व्यक्तियों के लिए किए गए कार्य ____________ हैं।
- A) other specified works
- B) deposit works
- C) miscellaneous works
- D) none of the options
Correct Answer: deposit works
Explanation: Explanation : funds are provided by the requesting agency/person on behalf of other departments, local bodies, or private individuals Works executed by the Railways —where —are classified as: These works are , but by , and are carried out as a service. Deposit Works
Q4. External screw threads can be produced fast by ____________ operation. ASTE 70% 2025 बाहरी स्क्रू थ्रेड्स को ____________ प्रक्रिया द्वारा तेजी से बनाया जा सकता है। ASTE 70% 2025
- A) Milling
- B) Chasing
- C) Casting
- D) Rolling
Correct Answer: Rolling
Explanation: Explanation : Limited to (steel, aluminium, brass). for producing external threads. Fastest method → metal is displaced → no chips. No material removal Thread Rolling –
Q5. The feature of IPMPLS that results in lower latency is __________. ASTE 70% 2025 IPMPLS की वह विशेषता जिसके परिणामस्वरूप कम विलंबता प्राप्त होती है, __________ है। ASTE 70% 2025
- A) multi protocol support
- B) label swtiching
- C) QOS
- D) all the options
Correct Answer: label swtiching
Explanation: Explanation : low-latency routing using Differentiated Services (DiffServ) Quality of Service (QoS) or, more specifically, or . packet. Every router within the network knows how to handle different Instead, every router uses the label as an index to identify a new FEC When a packet enters the MPLS network, a forwarding equivalence class (FEC) value is assigned to it by adding a small label to the FEC labels, so there is no need to do a header analysis each time. for that packet. MPLS creates a predetermined path to route traffic in the most efficient way possible based on the FEC label. This mechanism gives routers the option to choose low-latency routes
Q6. The plan head PH-12 covers the works of ____________. यो जना शी र्ष र्ष PH-12 में में _______ का र्य र्य शा मि ल हैं हैं। CBT ASTE 70% 2025. योजना शीर्ष PH-12 ____________ के कार्यों को कवर करता है। यो जना शी रश रश PH-12 में _______ का रय रश शा मि ल हैं। सीबीटी एएसटीई 70% 2025।
- A) purchase of new lines
- B) electrification
- C) taking over line wires from BSNL department
- D) training / HRD
Correct Answer: purchase of new lines
Explanation: Explanation : PH No PH Name The Minor heads (Plan Heads) of classification are follows- 11 - New lines (construction) 12 - Purchase of new lines. 13 - Restoration of dismantled line. 14 - Gauge conversion. 15 - Doubling. 16 - Traffic facilities – Yard remodeling and others. 22 - Rolling Stock. 32 - Track Renewals. 33 - Bridgework. 34 - Signaling and Telecommunication works. 35 - Taking over of line wires from P&T deptt. 36 - Electrification project. 37 - Other electrical works. 41 - Machinery and plants. 42 - Workshops including production units. 52 - Staff quarters. 53 - Amenities for Staff. 54 - Passenger amenities and other Rlys. Users amenities. 61 - Investment in Government commercial undertaking- Public undertaking. 64 - Other specified works. 71 - Stores suspense. 72 - Manufacturing suspense. 73 - Miscellaneous Advances. 81 - Metropolitan transport projects. Plan Head Coordinator Divisional Zonal Rly/PU 11 New Lines Sr.DOM PCOM 14
Q7. Automatic signalling shall not be provided on sections with continuous falling gradients steeper than______. ASTE 70% 2025. ______ से अधिक तीव्र निरंतर ढलान वाले खंडों पर स्वचालित सिग्नलिंग प्रदान नहीं की जाएगी। ASTE 70% 2025.
- A) 1 in 100
- B) 1 in 80
- C) 1 in 80 unless the brake power of the trains on the section is adequate to enable the trains being stopped at the signal 80
- D) none of the options
Correct Answer: 1 in 80 unless the brake power of the trains on the section is adequate to enable the trains being stopped at the signal 80
Explanation: Explanation : halves. It shall not be provided in a Block section with heavy and continuous provided in a Block section with heavy and continuous falling gradients steeper the trains being stopped at each of the Automatic Stop Signals. Automatic signal shall be located normally with a spacing of one km from each other subject to other considerations and headway required. It shall not be than 1 in 80 unless the brake power of trains on the section is adequate to enable Intermediate block signal shall be located, so as to split block section into near falling gradients steeper than 1 in 80 unless the brake power of trains on the
Q8. The authority to define similar nature of works for S&T works being executed by construction units is _______________. निर्मा र्माणयू यूनि टों टों द्वा रा नि ष्पा दि त कि ए जा रहे हे एस एं एं ड टी का र्यों के के लि ए समा न प्रकृ कृ ति के के का र्यों को परि भा षि त करने ने का प्रा धि का र _______ के के पा स है है। CBT ASTE 70% 2025 निर्माण इकाइयों द्वारा निष्पादित एस एंड टी कार्यों के लिए कार्यों की समान प्रकृति को परिभाषित करने का अधिकार _______________ है। निर्मा रामानु यूनी टों टों द्वा रा नि शपा दी त कि ए जा रहे हे एस ए एन एन डी टी का रयोन के ली ए समा न प्रकृति क्र त के के का रयोन को परी भा शि त करने ने का प्रा धी का र _______ के के पास स है। सीबीटी एएसटीई 70% 2025
- A) CAO
- B) GM
- C) Railway Board
- D) PCSTE
Correct Answer: PCSTE
Explanation: Explanation : in tenders (to ensure suitable contractors) "similar nature of works" In railway construction and contracting, refers to: A of types of works which require . grouping or classification Important for: similar skill sets, materials, and execution processes “The authority to define the similar nature of works shall rest with the head of the technical department concerned.” Eligibility criteria (past experience of similar works) Assessment of credentials
Q9. As per the latest Railway Board guidelines, two OFCs of ______ cores are to be laid for Kavach works. ASTE 70% 2025 रेलवे बोर्ड के नवीनतम दिशानिर्देशों के अनुसार, कवच कार्यों के लिए ______ करोड़ के दो ओएफसी बिछाए जाने हैं। ASTE 70% 2025
- A) 96 fibre
- B) 48 fibre
- C) 24 fibre
- D) 128 fibre
Correct Answer: 96 fibre
Explanation: Explanation : (i) There should be 2 OFC cables of 48 fibers each (96 fibers) on each side of the track. (ii) Zones shall carry out section wise gap analysis for provision of 2×48 fibers (96 Fibers) on each side of track duly taking in account the already laid OFC cable in last 10 years in the section and existing various provisions of OFC already covered in sanctioned works. the issue of OFC cable laying has been reviewed by Board and in order to avoid duplicity of OFC cable laying works, the following has been decided:
Q10. The minimum length of the track circuit shall be not less than _____________. ASTE 70% 2025. ट्रैक सर्किट की न्यूनतम लंबाई ____________ से कम नहीं होनी चाहिए। ASTE 70% 2025.
- A) minimum wheel base of any vehicle
- B) independent of wheel base of any vehicle
- C) maximum wheel base of any vehicle
- D) none of the options
Correct Answer: maximum wheel base of any vehicle
Explanation: Explanation : (c) Minimum Length: The length of a track circuit shall not be less than the two rail lengths (26 meters). track. Single Rail track circuit for D.C track circuit and Double Rail track circuit for Track Circuits General (a) A closed type track circuit shall be provided to prove the clearance of rail (b) Double rail track circuits shall be provided on non-RE areas. In RE areas, AFTC shall be used. maximum wheel base of any vehicle . The Track circuits shall cover at least
0