Knowledge Booster: EXPENDITURE Edition (08 Sep 2026)
Welcome to today's EXPENDITURE Knowledge Booster! We've handpicked 10 essential questions from our database to help you sharpen your skills. Dive in and test your knowledge!
Q1. As 'cash' forms, on an average about ___________ of the total expenditure of a Railway, Exchequer Control has the merit of providing an effective means of monitoring a substantial part of the expenditure on a day-to-day basis. चूंकि, रेलवे के कुल व्यय का औसतन लगभग ___________ 'नकद' होता है, राजकोष नियंत्रण में दिन-प्रतिदिन के आधार पर व्यय के एक बड़े हिस्से की निगरानी का एक प्रभावी साधन प्रदान करने की योग्यता होती है।
- A) 30 %
- B) 90 %
- C) 70 %
- D) 50 %
Correct Answer: 70 %
Explanation: Explanation : Budgetary Control – Covers Cash and Adjustments. Part of Ways and Means
Q2. PEI stands for __________________ (Hint: Efficiency indicator for Divisions) PEI का मतलब __________________ है (संकेत: डिवीजनों के लिए दक्षता संकेतक) PEI का मतलब __________________ है (संकेत: डिवीजनों के लिए दक्षता संकेतक) PEI का मतलब __________________ है (संकेत: डिवीजनों के लिए ज्वॉइंटर भर्ती)
- A) Performance Energy Index
- B) Performance Efficiency Index
- C) Primary Efficiency Index
- D) Primary Energy Index
Correct Answer: Performance Efficiency Index
Explanation: Explanation : DIVISIONS and PEI - Performance Efficiency Index A
Q3. EPC - The total amount of Damages (on account of delay of completion of the works) shall not exceed __________ of the Contract price ईपीसी - नुकसान की कुल राशि (कार्य पूरा होने में देरी के कारण) अनुबंध मूल्य के __________ से अधिक नहीं होगी
- A) 2 Percent
- B) 3 Percent
- C) 5 Percent
- D) 10 Percent
Correct Answer: 10 Percent
Explanation: Explanation : Damages due to delay in completion of the Work: 1. 0.05 % of the Contract Price for delay of each day reckoned from the date specified in the above Milestones. 2. Maximum is 10 % of the Contract Price.
Q4. RCM Stands for ____ (Hint: GST) आरसीएम का मतलब ____ है (संकेत: जीएसटी)
- A) Revenue Cycle Management
- B) Reverse Cycle Mechanism
- C) Reverse Charge Mechanism
- D) Reverse Charge Maintenance
Correct Answer: Reverse Charge Mechanism
Explanation: Explanation : Reverse charge means the liability to pay tax is on the recipient of goods or services instead of supplier of such goods or services. रिवर्स चार्ज का मतलब है कि कर का भुगतान करने का दायित्व ऐसी वस्तुओं या सेवाओं के आपूर्तिकर्ता के बजाय वस्तुओं या सेवाओं के प्राप्तकर्ता पर है।
Q5. Source of Finance 28 represents Capital N. N stands for वित्त का स्रोत 28 पूंजी एन को दर्शाता है। एन का मतलब है
- A) New
- B) Normal
- C) Non
- D) None of these
Correct Answer: None of these
Explanation: Explanation :
Q6. Who can exercise the same powers of PHOD in his/her absence? उसकी अनुपस्थिति में PHOD की समान शक्तियों का प्रयोग कौन कर सकता है?
- A) HOD
- B) PHOD of another Dept
- C) AGM
- D) CHOD
Correct Answer: CHOD
Explanation: Explanation : Mentioned in the Preamble of Model Schedule of Powers (MSOP)
Q7. Purpose of completion report is पूर्णता रिपोर्ट का उद्देश्य है
- A) To compare the cost of the work
- B) To close the accounts of the work
- C) To regularise the excess over-sanctioned estimate
- D) All of the above
Correct Answer: All of the above
Explanation: Explanation : Objects: 1. To compare the cost of work actually constructed with those provided in the last sanctioned estimate. 2. To close the accounts of the work. 3. To serve as a lesson to prepare the estimates for similar future works more realistically. 4. To regularise the excess over-sanctioned estimate 5. To transfer the expenditure reported in CR to Open Line through TWFA उद्देश्य: 1. पिछले स्वीकृत अनुमान में प्रदान की गई लागत के साथ वास्तव में निर्मित कार्य की लागत की तुलना करना। 2. कार्य के खाते बंद करना। 3. इसी तरह के भविष्य के कार्यों के अनुमान को अधिक यथार्थवादी ढंग से तैयार करने के लिए एक सबक के रूप में कार्य करना। 4. स्वीकृत अनुमान से अधिक को नियमित करना। 5. सीआर में रिपोर्ट किए गए व्यय को टीडब्ल्यूएफए के माध्यम से ओपन लाइन में स्थानांतरित करना।
Q8. A two packet system of tendering is mainly adopted to _________ निविदा की दो पैकेट प्रणाली मुख्य रूप से _________ के लिए अपनाई जाती है
- A) Get wider participation
- B) Restrict the competition
- C) Assess the Tenders technically without being influenced by the Financial bids
- D) None of the above
Correct Answer: Assess the Tenders technically without being influenced by the Financial bids
Explanation: Explanation :
Q9. Departmental charges are applicable for ______________ विभागीय शुल्क ______________ के लिए लागू हैं
- A) Works Contracts
- B) Service Contracts
- C) Both A & B
- D) Works Contracts, Service Contracts & Supply Contracts
Correct Answer: Works Contracts
Explanation: Explanation : Old name of Departmental charges is D&G Charges
Q10. In the exercise of their financial powers, the ______________ must pay due regard to the Canons of Financial Proprietyअपनी वित्तीय शक्तियों के प्रयोग में, ______________ को वित्तीय औचित्य के सिद्धांतों का उचित ध्यान रखना चाहिए
- A) Accounts officers
- B) DRMs
- C) GMs
- D) Sanctioning authorities
Correct Answer: Sanctioning authorities
Explanation: Explanation :