Knowledge Booster: EXPENDITURE Edition (26 Aug 2026)
Welcome to today's EXPENDITURE Knowledge Booster! We've handpicked 10 essential questions from our database to help you sharpen your skills. Dive in and test your knowledge!
Q1. GM/DRM - Have Powers to incur the expenditure _________ per annum for Repairs to the Railway Quarters जीएम/डीआरएम - रेलवे क्वार्टरों की मरम्मत के लिए प्रति वर्ष _________ व्यय करने का अधिकार रखते हैं
- A) Rs.50 Lakhs
- B) Rs. 1 Crores
- C) Rs. 2 Crores
- D) None of these
Correct Answer: None of these
Explanation: Explanation : The Correct Answer is Full Powers.
Q2. On expiry of Lease / LIcense / Way Leave agreement, further renewal up to _____________ or for a period as stipulated in the Agreement can be done based on the mutual agreement between Railway and the Party. लीज/लाइसेंस/वे लीव समझौते की समाप्ति पर, रेलवे और पार्टी के बीच आपसी समझौते के आधार पर _____________ तक या समझौते में निर्धारित अवधि के लिए आगे नवीनीकरण किया जा सकता है।
- A) 25 years
- B) 35 years
- C) 99 years
- D) None of the above
Correct Answer: 35 years
Explanation: Explanation : Railway Land Management Policy Source
Q3. In Model SOP (Schedule of Powers), Part D covered about ______ मॉडल एसओपी (शक्तियों की अनुसूची) में, भाग डी में ______ के बारे में बताया गया है
- A) Stores
- B) Establishment
- C) Medical
- D) Security
Correct Answer: Stores
Explanation: Explanation : Parts of MSOP
Q4. Completion Estimates are prepared for the major construction projects ____________ before the scheduled completion of the project for assessing the status of the work.It is a stock taking estimate कार्य की स्थिति का आकलन करने के लिए परियोजना के निर्धारित समापन से पहले प्रमुख निर्माण परियोजनाओं के लिए समापन अनुमान तैयार किए जाते हैं। यह एक स्टॉक लेने वाला अनुमान है
- A) Two Years
- B) Half year
- C) One year
- D) One and half years
Correct Answer: One and half years
Explanation: Explanation : Completion Estimate: (for Construction works).
Q5. IRFC stands for _____________ (Hint: source of Finance) IRFC का पूरा नाम _____________ है (संकेत: वित्त का स्रोत)
- A) Indian Railway Finance Corporation
- B) Indian Railway Finance Company
- C) Indian Railway Fiscal Corporation
- D) None of these
Correct Answer: Indian Railway Finance Corporation
Explanation: Explanation : मुख्यालय: नई दिल्ली Dedicated borrowing arm of Indian Railways
Q6. Service Contracts - Acceptance power of DRMs is ____________________ सेवा अनुबंध - डीआरएम की स्वीकृति शक्ति ____________________ है
- A) Above Rs. 20 Crore and up to Rs. 100 Crore
- B) Above Rs. 50 Crore and up to Rs. 100 Crore
- C) Above Rs. 20 Crore and up to Rs. 50 Crore
- D) Above Rs. 100 Crore and up to Rs. 500 Crore
Correct Answer: Above Rs. 20 Crore and up to Rs. 100 Crore
Explanation: Explanation : Source: Railway Board Letter No.2023/F(X)II/PW/1 dated 27.12.2023 Recruitment Tenders - Chairman RRB can exercise the powers of CHOD (i.e., up to Rs. 500 Crores)
Q7. Which one is not chargeable to DF - Development Fund Part III - Unremunerative Projects for improvement of Operational efficiency कौन सा डीएफ के लिए प्रभार्य नहीं है - विकास निधि भाग III - परिचालन दक्षता में सुधार के लिए अलाभकारी परियोजनाएं
- A) Improvement in water supply at stations for loco traffic purposes
- B) Electric lighting of sheds and stations, whether new works or improvements to existing ones.
- C) Provision of, and improvements and additions to, drivers and guards running rooms and rest houses for officers and subordinates.
- D) Provision and improvement of sanitation, water supply, roads, lighting and marketing facilities in railway colonies
Correct Answer: Provision and improvement of sanitation, water supply, roads, lighting and marketing facilities in railway colonies
Explanation: Explanation : It is chargeable to Development Fund Part II - Labour Welfare Works यह विकास निधि भाग II - श्रम कल्याण कार्यों के लिए प्रभार्य है
Q8. The Minor Head for Credits or Recoveries for the erstwhile Demands 04 to 13 is ______ पूर्ववर्ती मांगों 04 से 13 के लिए क्रेडिट या वसूली के लिए लघु शीर्ष ______ है
- A) 100
- B) 500
- C) 800
- D) 900
Correct Answer: 900
Explanation: Explanation : D. 900 (Credits & Recoveries) D.Nos – 04 to 13 – 900
Q9. SPE stands for ________________ (Hint: Investigation agency for loss of cash, stores or other railway property) एसपीई का मतलब ________________ है (संकेत: नकदी, स्टोर या अन्य रेलवे संपत्ति के नुकसान के लिए जांच एजेंसी)
- A) Special Police Enquiry
- B) Secret Police Enquiry
- C) Special Police Establishment
- D) None of these
Correct Answer: Special Police Establishment
Explanation: Explanation : CBI - Central Bureau of Investigation is established on SPE only सीबीआई - केंद्रीय जांच ब्यूरो एसपीई पर ही स्थापित है
Q10. Performance Guarantee in Service contracts___ % of contract value. सेवा अनुबंधों में निष्पादन गारंटी अनुबंध मूल्य का___%।
- A) 10%
- B) 5%
- C) 3%
- D) 6%
Correct Answer: 5%
Explanation: Explanation : PG - Performance Guarantee - 5 % of the Contract Value. (from 24th May 2024 onwards. Earlier it was 10%)